New Mexico’s top court denies Project Jupiter request to partially resume air quality case

The New Mexico Supreme Court denied Project Jupiter developer Yucca Growth Infrastructure’s request to partially resume proceedings in the data center’s paused air quality permit case.

New Mexico’s top court denies Project Jupiter request to partially resume air quality case
The New Mexico Supreme Court has denied Project Jupiter developer Yucca Growth Infrastructure’s request to partially resume proceedings in the data center’s paused air quality permit case. (Courtesy photo / Alexa Reynaud, Food & Water Watch, with aerial support provided by LightHawk)

Justices unanimously rejected Yucca Growth Infrastructure’s request to partially restart proceedings in the paused air quality permit case for the Doña Ana County data center

Joshua Bowling, Source New Mexico

This article was originally published by Source New Mexico.

The New Mexico Supreme Court on Tuesday unanimously denied a request from Project Jupiter’s developers to partially resume proceedings on the New Mexico Environment Department’s air quality permit application hearing for the massive data center under construction in Doña Ana County.

The Supreme Court in August paused the air quality permit hearing, which was scheduled to begin Sept. 14, after the Santa Fe-based clean energy organization New Energy Economy filed a petition arguing that the hearing was premature since a natural gas pipeline needed to fuel the project has yet to clear its own regulatory hurdles.

Yucca Growth Infrastructure, one of Project Jupiter’s developers, in its own Supreme Court filing argued that the justices should partially resume proceedings, particularly by allowing attorneys on both sides of the matter to submit their pre-hearing filings.

The New Mexico Environment Department has until Nov. 23 to make a final decision on Project Jupiter’s air quality permit, and keeping the hearing paused could run the risk of making that deadline “impossible to meet,” Yucca Growth Infrastructure’s attorneys wrote.

Project Jupiter hearing officer recuses after groups allege bias
Project Jupiter hearing officer Max Shepherd has recused himself after environmental groups alleged bias in the air-permit proceeding.

In a unanimous filing Tuesday afternoon, the state Supreme Court justices denied the developer’s request without further comment.

“A developer cannot manufacture an emergency and then use that emergency to strip the public of meaningful participation,” Mariel Nanasi, New Energy Economy’s executive director, said in a statement. “Project Jupiter chose its technology, chose its schedule, and chose to pursue construction while critical governmental approvals remained unresolved.”

A spokesperson for Yucca Growth Infrastructure did not immediately respond to a request for comment.

Other parties to the case, including the New Mexico Environment Department, had until Wednesday to file responses of their own. NMED did not immediately respond to a request for comment. 

Wednesday also marked the deadline for the Office of the State Engineer to file a response in a related Supreme Court case, in which the Center for Biological Diversity accused it of violating state law by approving the drilling of an emergency well for Project Jupiter without first holding a public hearing.

Joshua Bowling is a senior reporter for Source New Mexico. He's reported in New Mexico, where he broke stories of lavish spending at Western New Mexico University and more, since 2022.

Keep Reading

Man sentenced to life plus 26 years for New Mexico crime spree that ended in Las Cruces — Zachary Babitz was sentenced in federal court for a robbery and carjacking spree that ended in Las Cruces after a crash and arrest.

Sunland Park officials warn state-line road closures could complicate emergency response — City officials say road closures along the El Paso-Sunland Park boundary could create delays for emergency responders and residents.

Amira pushes back on New Mexico lawmakers as questions over reading software widen — The company disputes concerns raised by 35 lawmakers as scrutiny continues over student recordings, data practices and oversight.

Cut through the noise

Sign up for our free email newsletter to receive the latest headlines from Organ Mountain News